BHEL commissions 363.3 MW gas turbine-based Combined Cycle Power Project in Tripura

ADVERTISEMENT
The public sector Bharat Heavy Electricals Limited (BHEL) today said it had successfully commissioned the second module of the 2x363.3 MW gas-based Combined Cycle Power Plant (CCPP) of ONGC Thermal Power Corporation (OTPC) in Tripura.
 
Located at Palatana in Udaipur district of Tripura, around 50 kms from Agartala, the CCPP comprises two modules of 363.3 MW each equipped with fuel efficient advanced class Frame 9FA Gas Turbines. 
 
BHEL had won the contract for setting up the CCPP on EPC (Engineering, Procurement & Construction) basis, against international competitive bidding (ICB), a press release from the company said.
 
With the commissioning of this module, BHEL has commissioned nine modules of Frame 9FA Gas Turbines in the combined cycle mode in the country, it said.
 
BHEL has so far commissioned 911 MW of gas-based and hydro sets in Tripura which accounts for 100% of the state's generating capacity. BHEL had earlier commissioned 14 gas turbines of smaller rating upto 21 MW in Tripura as the sizes were limited by logistic constraint. 
 
The Palatana project is the first and the largest of its kind in the entire North-Eastern part of India. BHEL is executing another gas-based project of 100 MW of NEEPCO at Monarchak in Tripura.
 
"Setting up the 726 MW power plant at Palatana was a herculean task. The harsh terrain, incessant rains, and inadequate road infrastructure made the conventional mode of transportation from BHEL's works in Hyderabad to the remote site almost impossible. To overcome logistical constraints, the consignments were transported through multi-modal means of transport, including waterways through Bangladesh under a special agreement with the Government of Bangladesh," the release said.
 
BHEL’s scope of work in the project involved design, engineering, manufacture, supply, erection and commissioning of two Frame 9FA gas turbine generator sets, two steam turbine generator sets and two heat recovery steam generators with state-of-the-art controls & instrumentation, associated auxiliaries and balance of plant, in addition to complete civil works and spares, it added.
 
BHEL had earlier commissioned the first module of the project in January, 2013 and it was dedicated to the ntion by President Pranab Mukherjee in June, 2013.
 
NNN
 
ADVERTISEMENT
 

See News Videos

Comments

Post new comment

The content of this field is kept private and will not be shown publicly.
  • Web page addresses and e-mail addresses turn into links automatically.
  • Allowed HTML tags: <a> <em> <strong> <cite> <code> <ul> <ol> <li> <dl> <dt> <dd> <canvas>
  • Lines and paragraphs break automatically.

More information about formatting options

© Copyright 2012 NetIndian. All rights reserved. Republication or redistribution of NetIndian content, including by framing or similar means, is expressly prohibited without the prior written consent of NetIndian Media Corporation. Write to info[AT]netindian[DOT]in for permission to use content. Read detailed Terms of Use.